When you import project risk data into Primavera Cloud, data that is sent from P6 EPPM to the application includes risk thresholds, risk matrixes, and data from the project risk register. After this data is imported into Primavera Cloud, you can perform a qualitative analysis to assess and prioritize the risks identified for your project. To run a more detailed quantitative analysis, you must also import schedule data from your P6 EPPM project. The system uses the activity data as inputs for the analysis process to determine how the identified risks can impact the durations and dates of your project activities.
|
|